Phone 0800 030 4391
Email >
- AIR TIGHTNESS CONSULTANCY & TESTING
- ENERGY, SAP, EPC, DEC & SBEM
- BREEAM & CODE FOR SUSTAINABLE HOMES
- ACOUSTIC CONSULTANCY & TESTING
- AIR SEALING & FIRE STOPPING
- THE COMPLETE PACKAGE
- Air Tightness Homepage
- Air Tightness - a Definition
- Commercial Benefits to the Building
Owner & Client - Information for the Client
- Information for the Architect
- Information for the Main Contractor
- Information for the Building Services Consultants
- Information for Material, Plant &
Component Suppliers - Information for Building Control
Officers & Approved Inspectors - Design Review
- Site Advice Visits
- Contracting Work
- Air Tightness Testing
- Air Test - Domestic Dwelling
- SAP Ratings
- SBEM Ratings
- Example Air Tightness Test
- Smoke Test
- Thermographic Surveys
- Energy Usage
- Flagship Projects
- Technical Info Packs/Video Downloads
- Brochure Request/Download
- Frequently Asked Questions
- Theory of Air Tightness
- Air Tightness - Related Services
Air Tightness - Site Advice Visits
HRS's on-site expertise was used to good effect by Laing O'Rourke on Swindon schools. The PFI contract specification included an item for them to achieve an air permeability rate of 10m³/h/m² at the final air test. By carrying out three site audits at critical stages of the construction programme, HRS enabled the air tightness specification to be met first time, with minimal disruption and extra costs.
Problem
LOR were already on-site and out of the ground on all the sites with sub-contracts placed for all the major packages of work. How could LOR ensure that the schools complied with the air tightness specification first time, without recourse to taking on any more sub-contractors, whilst retaining control and responsibility for the air tightness specification and final air tightness test result?
Solution
HRS visited all sites and liased directly with the LOR Project Engineer to carry out detailed Site Audits. First, a design review was carried out on-site with the LOR Project Engineer. Aspects of the design, specification and/or construction were highlighted if there was any significant risk of an air leakage path being created. Details were noted, photographed and recorded in an audit schedule, with recommendations made for remedial works. Subsequently, visits to site were made on dates arranged during the first visit to coincide with critical dates on the construction programme. All areas of concern noted in the schedule were inspected along with any new works that were complete. A new detailed schedule was built up and presented to the LOR Project Manager. HRS also provided attendance during the air tightness tests to ensure the tests were set-up and carried out correctly.
HRS Services Capabilities
HRS Services send experienced Contract/Operation Managers to inspect air sealing works at any stage of construction, even after an air tightness test if the result was poor. This can be the first stage in preventing or resolving a problem. Terms of reference may address the correct fitting of specified materials, omissions at design stage, problems with building technique or producing a schedule for remedial action. Reports are usually delivered in hard copy but, where speed is the priority, e-mail or CD are options.
Air Tightness - Flagship Projects
Click headings to read more
Air test result
Tightest building in UK Air test result <0.5 m³/hour/m², HRS involved throughout
Air Tightness Consultancy
IKEA employed the UK's largest fan to check the air tightness of its Glasgow store
Poor Building Envelope Performance - Case Studies
A Complete Solution For Investigating, Analysing Problems and Providing Solutions

